Supply, installation, testing and commissioning of electrical works for Texas WWTP upgrade. Lump sum contract under AS 4000:2025. Completion required by 17 December 2027. Tender closes 4:00 PM EST, 10 November 2026. No mandatory site visit. 12-month workmanship warranty. Retention: 10% of progress payments. Public liability insurance minimum $20M. Submissions via Vendor Panel. Prices inclusive of GST.
Completion of all works, including commissioning, is required by 17 December 2027. The contract states: completion of all components of the works, including commissioning, is required by 17 december 2027.
Progress claims may be submitted for works fully executed on site or materials delivered to site. The contract states: progress claims may be submitted for works fully executed on site, including any associated labour, plant, and installation, or for materials procured and delivered to site ready for use.
The contractor provides a 12-month warranty on all workmanship from practical completion. The contract states: the contractor is responsible to provide 12 months warranty on all workmanship from the date of the practical completion inspection.
The works shall be undertaken by a suitably qualified, experienced and appropriately licensed electrical contractor. The document states: the works shall be undertaken by a suitably qualified, experienced and appropriately licensed electrical contractor with the skills and resources necessary to complete the works safely.
Failure to maintain progress may result in liquidated damages. The contract states: failure to maintain progress in accordance with the approved project schedule. . . may constitute a breach of the contract and may result in the application of liquidated damages.
There is no mandatory site visit, but requests are welcome. The document states: there is no mandatory site visit for these works but requests for a site visit during the tender period are welcome.
All enquiries must be submitted via the Vendor Panel question portal. The document states: all enquiries and communication regarding this tender must be submitted via the vendor panel question portal.
Direct contact with council employees, councillors, or consultants is strictly prohibited. The document states: any breach of this protocol, including direct contact outside the approved channel, will result in automatic disqualification from the contracting process.