Bundaberg Regional Council seeks a principal contractor for Stage 2 upgrade of McIlwraith Road between CH ****, including pavement rehabilitation, widening, safety improvements, drainage works, and sealing. Offers due 17 November 2026 via Vendor Panel. No mandatory site inspection. Evaluation based on price (50%) and non-financial criteria (50%). Security required at 5% of contract value. Liquidated damages $1,**** per day. Defects liability period 12 months.
Practical completion is scheduled for 2 July 2026, as stated: practical completion 2 july 2026. Tenderers should submit their proposed delivery program for assessment.
Payment claims are monthly, with the principal to pay within 15 business days after receipt of a claim, as stated: within 15 business days after receipt by the superintendent of a claim for payment, the principal shall pay.
The defects liability period is 12 months, as stated: the defects liability period: 12 months. The contractor must rectify defects within this period.
Evaluation is based on financial score (50%) and non-financial criteria (50%), as stated: financial score 50 and nonfinancial evaluation criteria and relative overall weightings 50.
Tenderers must demonstrate experience in similar projects within the last 5 years, as stated: suitably experienced tenderers that can demonstrate by recent projects within the last 5 years, capacity of carrying out the works.
Liquidated damages are $1,**** per day, as stated: liquidated damages per day: 1**** per day actual cost reimbursement to the principal.
There is no mandatory briefing, but tenderers may inspect the site without permission, as stated: there will be no mandatory briefing meeting for this invitation to offer. should tenderers wish to visually inspect the site, they are able to do so without express permission.
Disputes must be notified within 28 days of a superintendent's direction, as stated: a notice of dispute in accordance with clause 47. 1 is given by one party to the other party within 28 days after the date of service on that party of the direction.
Non-conforming submissions, including failure to submit returnable schedules or late offers, will be considered non-conforming, as stated: tenderers who fail to submit any of the returnable schedules or associated appendices with their offer, shall be considered to have made a nonconforming submission.