The tender is for the replacement of roof sheeting, gutters, capping, downpipes, barge and fascia boards, purlins and bird netting, and painting works at Porton Barracks, QLD. A mandatory industry briefing will be held on March 10, 2026, and registration is required by March 6, 2026. The tenderer must complete and return the signed confidentiality agreement. The closing date for questions is seven days before the tender close date. The tenderer must provide a lump sum contract price and a breakdown of the price. The project is a major construction project for the purposes of the australian skills guarantee procurement connected policy. The tenderer must complete and lodge tenderschedulem australian skills guarantee. The tenderer must complete and lodge a supplier environmental sustainability plan by responding to tenderschedulel environmentally sustainable procurement. The tenderer must complete and lodge tenderschedulej statement of tax record. The tenderer must complete and lodge tenderschedulek whs accreditation scheme accreditation. The tenderer must complete and lodge tenderschedulee indigenous procurement policy. The tenderer must provide details of the insurances which it has or proposes to put in place for the purposes of the contract in part5. The tenderer must provide details of its practices regarding labour regulations and ethical employment practices. The tenderer must provide details of its practices regarding promoting environmental sustainability in relation to the contractors activities and the works. The tenderer must provide details of its practices regarding achieving efficiencies and savings in whole of life costs. The tenderer must demonstrate its capability to meet the applicable standards. The tenderer must provide details of its organisational commitment to ethical conduct and ensuring compliance with the commonwealth supplier code of conduct. The tenderer must provide a detailed program showing its order of work, periods for carrying out all construction activities, including offsite activities and key dates. The tenderer must provide a proposed date for completion. The tenderer must provide a table of variation rates and prices. The tenderer must provide its maximum amount of delay damages. The tenderer must demonstrate how an alternative proposal will achieve greater value for money. The tenderer must provide details of the terms and levels of the insurances which the tenderer has or proposes to put in place for the purpose of clauses 4. 3 4. 6 of the conditions of contract in part5. The tenderer may identify any specific information provided by the tenderer to the commonwealth that it wishes the commonwealth to keep confidential and must provide justification, in accordance with paragraph c, why the information identified under paragraph a should be kept confidential. The tenderer must confirm whether or not it currently holds disp membership and, if so, provide details of such membership in item a and if the tenderer does not currently hold disp membership or if the tenderer does not comply with the requirements under the contract relating to the disp, complete the questionnaire in item b. The tenderer must provide and attach each of the valid and satisfactory strs referred to in the table below as required for the tenderers entity type. The tenderer must provide evidence of accreditation in accordance with the whs accreditation scheme by attaching a copy of its accreditation issued by the federal safety commissioner and any expiry dates for such accreditation or the steps taken to obtain accreditation in accordance with the whs accreditation scheme, including any application and correspondence with the office of the federal safety commissioner. The tenderer must complete and lodge a supplier environmental sustainability plan in the form of the sesp template and provide the esp policy commitment report in the form required as a spreadsheet in excel format only and not as an embedded imagescreensho
The tenderer is requested to provide a proposed date for completion as defined in clause 24. 1 of the conditions of contract in part5 which should have regard to the commonwealths nominated date for completion in the table below, however provision of a date after this nominated date will not render the tender nonconforming: if there are no stages, for the works date for completionnominated date for completioninsert months after the award datewithin 6 months after the award dateincluding 6 weeks of hoto review and approval notes: 1. tenderers to ensure that the hoto draft omms, as builts, gdls etc. is submitted early before physical completion and allow at least 6 weeks for hoto review and approval process. 2. the commonwealth is interested in proposals that would greatly benefit the programme and provide schedule efficiencies in the delivery of the project. as such, tenderers are encouraged to lodge alternative proposals in tender schedule h in respect of the works description only in pursuit of greater value for money and shorter timeframe for delivering the works.
The tenderer is requested to provide the times for submission of payment claims for the purposes of clause 11. 2a of the conditions of contract in part5 as follows: imes for submission of payment claims monthly on the 15th day of each monththe tenderer is also requested to provide an anticipated monthly cash flow for payment of the contract price.
The commonwealth will apply the following evaluation criteria: project understanding 50 weighting, workload and proposed resources 15 weighting, previous performance 15 weighting, program 20 weighting, indigenous procurement policy no weighting, commonwealth procurement rules compliance no weighting, financial no weighting, alternative proposals if any no weighting, miscellaneous matters for evaluation: security if applicable, insurance details and levels and tenderers commercialinconfidence information no weighting, and information security no weighting.
The conditions for participation applicable to this tender process are that the tenderer must: complete and return the signed confidentiality agreement. The tenderer should note that this is athese are conditions for participation in this tender process under clause 3. 1c of the tender conditions and it is requested to lodge information in its tender demonstrating that it meets each condition for participation. If the tender is lodged on a joint bid basis, the tenderer is requested to lodge this information for each joint bid party as applicable.
The tenderer is requested to provide its maximum amount of delay damages for the purposes of clause 9. 6 of the conditions of contract in part5 together with a breakdown as to how the relevant amount has been calculated as follows: if there are no stages, the maximum delay damages for the works insert per working daybreakdown of calculation of maximum amount of delay damagesinsert
A mandatory industry briefing will be held on March 10, 2026, and registration is required by March 6, 2026. Time for industry briefing: 11: 00am 1: 00pm aestdate for industry briefing: 10th march 2026location: porton barracks 1 macbar ct, edmonton **** point: pass officemaximum number of tenderer personnel permitted to attend the industry briefing: 1 other information required: none stated other requirements: tenderers must register to attend the industry briefing see time and date for tenderer details for industry briefing below. tenderers must not enter site without being escorted by the contract administrator. for site industry brief, all attendees must complete the national base induction prior to attendance at a defence base.
The cutoff date for questions pertaining to this tender is seven 7 days before the tender close date.