Design and construct upgrade of Gundagai WTP CCP instrumentation and integration, with optional chemical dosing and actuator valve upgrades. Mandatory site inspection on 12 October 2026 at Gundagai WTP. Tender closes 12 November 2026. Completion within 20 calendar weeks, by 30 April 2027. Liquidated damages AUD **** per day. Retention 4% via bank guarantee. Professional indemnity insurance AUD 5 million required. Payment claims monthly.
The time for completion is 20 calendar weeks after acceptance of the tender, and must be completed before 30 April 2027, including optional items if selected. The time for completion is: 20 calendar weeks after the date of acceptance of the tender.
Payment claims are to be made monthly, on and after the 25th day of each calendar month. The principal must pay within 15 business days after the claim is served. Payment claims are to be made: monthly, on and after 25th day of each calendar month.
After completion, the principal may instruct the contractor to make good any defect within a specified time. All costs associated with making good a defect are payable by the contractor. All costs associated with making good a defect are payable by the contractor.
The council is seeking submissions from suitably qualified and experienced contractors for the design and construction of upgrades. Seeking submissions from suitably qualified and experienced contractors for the design and construction of upgrades.
Liquidated damages are AUD **** per day for late completion. The rate per day for liquidated damages is: ****.
A mandatory site inspection will be held on Monday 12 October 2026 at 11:00 am at the Gundagai Water Treatment Plant. A mandatory site inspection will be held as per the details provided below.
If dissatisfied, the contractor must notify the authorised person and senior executive in writing within 10 business days after the act or omission. Within 10 business days after. . . the contractor is to notify the authorised person and the senior executive in writing of a dispute.
Failure to attend the mandatory site inspection may result in disqualification. The tenderer must familiarise themselves with the works and the site before submission. The tenderer must familiarise themselves with the works and the site before submission.