Tenders from qualified contractors for sewer mains replacement in Cootamundra. Mandatory site inspection on 19 October 2026 at 11:00 AM at council office. Completion within 16 calendar weeks, by 30 April 2027. Liquidated damages **** per day. Retention 4% or undertaking. Payment claims monthly. Professional indemnity insurance required. Questions close 29 October 2026, tender closes 3 November 2026.
The time for completion is 16 calendar weeks after acceptance of tender, with the project needing completion by 30 April 2027. As stated: sewer mains project need to be completed by 30 april 2027.
Payment claims are made monthly, on and after the last business day of each calendar month. Payment by principal is due within 15 business days after the claim is served. As stated: payment claims are to be made: monthly, on and after the last business day of each calendar month.
The post completion period is 52 calendar weeks, starting the day after completion. Defects must be made good at contractor's cost. As stated: the post completion period, which 52 calendar weeks. starts on the day after the work under the contract reaches completion.
Tenders are sought from suitably qualified and experienced contractors to undertake sewer mains replacement works. The contractor must complete design to the extent of clauses 3. 4 and 3. 9, including minor items and shop detailing.
Liquidated damages are **** per day for late completion. As stated: the rate per day for liquidated **** damages is: if no rate or nil or 0 or na is stated, then common law damages apply.
A mandatory site inspection will be held on Monday 19 October 2026 at 11:00 AM at the council office. As stated: a mandatory site inspection will be held as per the details provided below odate: monday 19 october 2026 otime: 11: 00 am.
Disputes must be notified within 10 business days after the act or omission. As stated: within 10 business days after: a the act or omission or b the expiry of a relevant period specified under clause **** or clause 15. 3, whichever is later, the contractor is to notify the authorised person.
Failure to attend the mandatory site inspection may risk disqualification. The tenderer must familiarise themselves with the works and site before submission. As stated: the tenderer must familiarise themselves with the works and the site before submission.