Construction of a shared path link along Whitelaw Avenue between Doug Dean Reserve and Sutton Street, Ballarat. Works include shared path, kerb and channel, raised crossings, solar lighting, drainage swales, carpark extension, landscaping, and 26 weeks landscape establishment. Contract is fixed lump sum, with 52-week defects liability period. Security required: 2 x 2. 5% of contract sum. Liquidated damages: $150 per day. Practical completion by 01/05/2027 or 60 days from execution. Payment claims due 30th business day monthly, payment within 30 days. Public liability insurance minimum $20 million. Tender closes 22 October 2026.
Practical completion is due by 01/05/2027 or 60 days from the execution date, as stated: date for practical completion clause 1. 1: **** or 60 days from the execution date.
Payment claims are due on the 30th business day of each month, with payment within 30 days after the payment schedule or tax invoice, as stated: period for payment clause 20. 3: 30 days after: a the issue of the payment schedule or b receipt of a tax invoice.
Defects liability period is 52 weeks, as stated: defects liability period clauses 1. 1 and 18. 1: 52 weeks.
Contractor must be registered in the Rapid Global Amalgamated Councils of Victoria database, as stated: the contractor must be registered in the rapid global amalgamated councils of victoria database and must maintain the required level of certification.
Liquidated damages are $150 per day for late completion, as stated: rate of liquidated damages clause 17. 1: 150 per day.
Failure to provide security within 5 business days after execution date prevents payment claims, as stated: if the contractor fails to do so, the contractor will not have any entitlement to submit any claim for payment until the contractor provides such security.