This is a public tender for the Cricket Facilities Relocation and Upgrade Project (Tender ****) by Rockhampton Regional Council. The project involves the construction of new cricket assets, including cricket wickets and training facilities nets, at two separate locations: Kéle Park and Kalka Shades. This relocation is to facilitate the movement of community organisations from the Victoria Park Cricket Grounds. The tender documents include General Conditions of Contract based on AS ****, with specific annexures detailing amendments and contract references. Key aspects covered include contract reference, annexures for contract conditions, performance guarantees, confidentiality, subcontractor covenants, and deeds of warranty. The contract specifies detailed requirements for security, insurance, site access, health and safety, environmental management, and dispute resolution. There are two separable portions for the project: Kéle Park Priority Works Project A and Kéle Park Kalka Shades Remainder of Project A Project B. The tender closes on April 22, 2026.
The date for practical completion for Separable Portion 1 (Kéle Park Priority Works Project A) is May 29, 2026, and for Separable Portion 2 (Kéle Park Kalka Shades Remainder of Project A Project B) is June 26, 2026.
The tender notice states that payments under the contract shall be made at Rockhampton, Queensland. Payment claims are to be submitted by the 15th day of each month, or the date of satisfaction of the last claim precondition, whichever is later.
The contract includes provisions for contractor warranties, including that the contractor is skilled in similar projects, will carry out works with due skill and diligence, has a clear understanding of the work, will use the best available materials, has an adequate organization, holds the appropriate license, and has complied with privacy obligations.
The contract requires the contractor to hold a licence of the appropriate class under the QBCC Act and be otherwise entitled to undertake the work. Specific key personnel are also required to be engaged and have equivalent skill and experience.
Liquidated damages per day are not applicable for Separable Portion 1 and Separable Portion 2. However, the contract includes provisions for substantial breach by the contractor, which may lead to termination and associated remedies.
The contract requires the contractor to visit the site prior to execution of the contract and to have made itself aware of all matters including site and local conditions affecting the works.
The supplier query cutoff date is Monday, April 20, 2026, 01:00 am.