Construct only contract for Vickers Rd PS C6B diversion project stage 1 rising main construction. Lump sum contract. Date for practical completion 28 January 2028. Liquidated damages $2,000 per day. Security: two unconditional bank guarantees or insurance bonds, 5% of contract sum. Working hours Monday to Saturday 6am to 6pm. Progress claims on 25th day of each month. Payment period 15 business days. Defects liability period 12 months. Site: Beck Dr to Dalrymple Road via Kern Drain. Tender closes 23 November 2026.
Date for practical completion is 28 January 2028, as stated in annexure part A item 8a: a date for **** practical completion.
Progress claims are due on the 25th day of each month, with payment period of 15 business days after the claim is received. Interest on overdue payments is 7% per annum.
Contractor warrants it will carry out and complete WUC in accordance with all requirements of the contract and all legislative requirements, and that the works will be free from defects.
Contractor must be registered and validated in the TCC contractor management system (CMS) and successfully complete the TCC online safety induction before accessing the site.
Liquidated damages are $2,000 per day, with no cap on aggregate liability, as stated in annexure part A item 29: liquidated 2,000 per day damages, rate.
Supplier query cutoff is Monday 16 November 2026, as stated in the request details: supplier query cutoff monday 16 november 2026.
Contractor must not engage in collusive tendering, anticompetitive conduct, or any other unlawful or unethical conduct, and must not attempt to improperly influence the principal's personnel.