Lump sum contract for construction of Maturation Pond 1 at Texas WWTP. Completion required by 17 December 2027. Tender closes 4pm EST 4 November 2026. No mandatory site visit, but optional visits available. Prices inclusive of GST. 10% retention from progress payments. 12-month warranty on workmanship. Evaluation based on price, past performance, methodology, WHS systems, and local content. All submissions via Vendor Panel.
Completion of all works, including commissioning, is required by 17 December 2027. Respondents must provide a schedule of works with their submission indicating estimated delivery timeframes. Completion of all components of the works, including commissioning, is required by 17 december 2027.
Progress claims may be submitted for works fully executed on site or materials delivered to site. A portion of each progress payment, equivalent to 10% of the value of work completed exclusive of GST, shall be retained as retention money. a portion of each progress payment, equivalent to 10 of the value of work completed exclusive of gst, shall be retained by council as retention money.
The contractor must provide 12 months warranty on all workmanship from the date of practical completion inspection. the contractor is responsible to provide 12 months warranty on all workmanship from the date of the practical completion inspection.
Submissions will be assessed on tendered prices, past performance, suitability of methodology, contractor WHS systems, availability, and local contractor content. submissions will be assessed on the following criteria: tendered prices, past performance experience of contractor and project team, suitability of methodology in the delivery of the works, contractor whs systems, availability, and local contractor local content
Contractors must have necessary skills and expertise, complete the WHS questionnaire, and provide details of relevant insurances including public liability of at least $10 million. the contractor warrants that it has the necessary skills and expertise to be able to competently supply the scope of works.
Failure to maintain progress may constitute a breach and may result in application of liquidated damages. failure to maintain progress in accordance with the approved project schedule. . . may constitute a breach of the contract and may result in the application of liquidated damages or other applicable contractual remedies.
There is no mandatory site visit, but requests for a site visit during the tender period are welcome. there is no mandatory site visit for these works but requests for a site visit during the tender period are welcome.
Any form of canvassing or direct contact with council employees, councillors, or consultants is strictly prohibited and will result in automatic disqualification. any breach of this protocol, including direct contact outside the approved channel, will result in automatic disqualification from the contracting process.