Cherbourg Aboriginal Shire Council invites tenders for design and construct of trunk infrastructure and a new storage shed (Shed J) for the Cherbourg Materials Recovery Facility upgrade. Contract **** completion within 100 calendar days after acceptance of tender. Security: two bank guarantees of 5% each. Liquidated damages: $500 per day. Defects liability period: 12 months. Professional indemnity insurance: $2,000,000 per claim. Public liability insurance: $20,000,000. Working hours Monday to Friday 7am-6pm, Saturday 7am-4pm. Progress claims on 21st day of each month. Queensland Charter for Local Content applies.
Practical completion is required within 100 calendar days after the date of acceptance of tender, as stated: period of time for practical completion clause 1 within 100 calendar days after the date of acceptance of tender.
Progress claims are due on the 21st day of each month for work done to that date, as stated: times for progress claims 21st day of each month in which wuc is carried out up to and including the month in which practical completion is reached.
Contractor warrants that all plant, equipment, materials and goods supplied shall be new, free from defects and of merchantable quality, as stated: be free from defects and of merchantable quality.
Contractor must be suitably qualified, skilled and experienced, holding all necessary licences and accreditations, as stated: hold, maintain and comply with the requirements of, all necessary competencies, licences, accreditations, qualifications, permits, clearances or other authorisations.
Liquidated damages are set at $500 per day, as stated: liquidated damages, rate subclause 34. 7 500 per day.
Engaging in improper conduct, including collusive tendering or attempting to improperly influence, is prohibited, as stated: engaging in any collusive tendering, anticompetitive conduct, or any other unlawful or unethical conduct.