Bundaberg Regional Council seeks a principal contractor for Stage 2 upgrade of McIlwraith Road between CH **** include pavement rehabilitation, widening, safety improvements, earthworks, drainage, sealing, signage, and barriers. Offers due 17 November 2026 via Vendor Panel. No mandatory briefing. Site inspection allowed without permission. Evaluation based on price (50%) and non-financial criteria (50%). Security required at 5% of contract value. Liquidated damages AUD **** per day. Defects liability period 12 months.
Practical completion is scheduled for 2 July 2026. Tenderers should submit their proposed delivery program and methodology for assessment. practical completion 2 july 2026
Payment claims are monthly, from each reference date. The principal shall pay within 15 business days after receipt of a claim. within 15 business days after receipt by the superintendent of a claim for payment, the principal shall pay
The defects liability period is 12 months. the defects liability period: 12 months
Evaluation criteria include financial score (50%) based on offer price and non-financial criteria (50%) assessing understanding, methodology, program, and risk mitigation. financial score 50 determined from a financial analysis model
Tenderers must demonstrate experience in delivering projects of similar scope and value, with minimum 1 project. The tenderer has experience in successfully delivering projects of similar scope and value minimum 1 project.
Liquidated damages are AUD **** per day, with no limit. liquidated damages per day: **** per day
There is no mandatory briefing meeting. Tenderers may visually inspect the site without express permission, but no invasive works are permitted. there will be no mandatory briefing meeting for this invitation to offer
A notice of dispute must be given within 28 days after the date of service of a superintendent's direction. a notice of dispute in accordance with clause 47. 1 is given by one party to the other party within 28 days
Non-conforming submissions, including failure to submit returnable schedules or late offers, will be considered nonconforming. Tenderers who fail to submit any of the returnable schedules or associated appendices with their offer, shall be considered to have made a nonconforming submission.