Lump sum tender for Ausgrid HV augmentation and associated works at Apex Park, Cessnock. Early works for park redevelopment including drainage, landscaping, carparking, lighting, shelters and footpaths. Pre-tender meeting on 28 October 2026 at 1pm at Apex Park. Tender closes 11 November 2026 at 2pm. Contract MW21LG general conditions. Evaluation criteria include price, methodology, experience, WHS, environmental and quality management, local and social procurement considerations.
The time for completion is 10 calendar weeks after the date of acceptance of the tender. the time for completion is: 10 calendar weeks after the date of acceptance of the tender.
Payment claims are to be submitted at times specified in contract information item 15. The principal must provide a payment schedule within 10 business days and payment within 15 business days after the claim is served. payment by the principal of the scheduled amount shown in the payment schedule is to be made within 15 business days after the contractors payment claim is served.
The contractor warrants that before close of tenders it has examined the site and surrounds, made enquiries, and not relied on the completeness of information provided by the principal. the contractor warrants that, before the close of tenders, it has: 1. examined the site and surrounds 2. made enquiries concerning the site
Evaluation criteria include price, methodology program, relevant experience and capability, WHS environmental and quality management, local consideration, and social procurement. evaluation criteria oprice omethodology program orelevant experience and capability owhs, environmental and quality management olocal consideration osocial procurement
If the contractor does not complete a milestone or the work in accordance with clause 11. 1, liquidated damages at the rate stated in contract information item 14 apply. if a rate is stated in contract information item 14, the contractor is to pay to the principal liquidated damages at that rate
If the contractor is dissatisfied with an act or omission of the principal, it must notify the authorised person and senior executive in writing within 10 business days. within 10 business days after: 1. the act or omission or 2. the expiry of a relevant period specified under clause **** or clause 15. 3, whichever is later, the contractor is to notify the authorised person and the senior executive in writing of a dispute.
If the contractor commits a substantial breach, including failing to carry out an instruction or not carrying out work at a reasonable rate, the principal may issue a notice and potentially terminate the contract. if the contractor commits a substantial breach of the contract, including: a failing to carry out an instruction of the principal within the time specified